Before Delivery
Please review the below before the delivery of your container
Table of Contents:
Review Documentation
Crane Expectations
Commissioning Preparation
Review Order Documentation
(back to top)
Giga Energy creates a Shared Google Drive that houses your specific order's documentation. This would've been sent to you by our Customer Support Team from customersupport@gigaenergy.com. The Shared Drive contains items such as:
Physical Container - Shelf layout, how the feeder wires come in from the transformer, and the specs of the container itself
Networking - Topology drawing and network switch specs
Switchgear - Electrical drawings/schematics, component BOM with manuals
Fans + Cooling - Specs for the exterior G1 and interior pleated paper filters as well as exhaust fan specs
If there is additional documentation or more information about a specific component you are needing, please Submit a Ticket and our Customer Support Team will be happy to assist.
Crane Expectations
(back to top)
Arrange a Crane
Line up your delivery date with Giga Energy's Order Management Team. You will need a crane onsite upon delivery to unload your unit. All cranes should be rated 20% above the nameplate weight. Below are the weights of the Giga Air Boxes.
NOTE: All weights below are WITHOUT miners
M Series 20’ weighs: 11,000 lbs.
L Series 40’ weighs: 21,000 lbs.
XL Series 45' weights: 24,250 lbs.
Commissioning Preparation
(back to top)
Arrange Electrician
Coordinate with an electrician to terminate your units. The earlier you line this up the better. Feel free to share the Electrical Documentation in your customer folder with them. This includes the bus bar specifications and Electrical Schematic
Do some initial due diligence with the authority having Jurisdiction (AHJ) to see what type of inspection is required. Although we use UL listed electrical components, we do not have a full unit certification or listing